Precast Concrete: ‘Barring’ of floor units causes major injuries and £33k fine
The use of pinch or crowbars to move components is a common practice in precast concrete erection. Components should be positioned as close as possible to minimise the need for it but there is often a need for some adjustment whether to ensure that the component reaches the right position or to tighten up a floor after laying.
If you have any questions on barring we would recommend you read the Precast flooring Federations Code of Practice for the Safety Installation of Precast Concrete Floors and Associated Components available here.
The incident to which the title refers occurred in December 2014 when Walter Thompson (Contractors) Limited, a construction company from Northallerton, was engaged as Principal Contractor for a 47 bedroom extension of the Ramside Hall Hotel, Durham.
£33,000 fine under CDM Regulations
An investigation by the Health and Safety Executive (HSE) into the incident found that the company had failed to adequately plan and manage the installation of the two-floor slabs.
The defendants pleaded guilty to breaching Regulation 22(1)(a) of the Construction (Design and Management) Regulations 2007 and was fined £33,000 with £12,552.81 costs.