Precast Concrete: ‘Barring’ of floor units causes major injuries and £33k fine

The use of pinch or crowbars to move components is a common practice in precast concrete erection.  Components should be positioned as close as possible to minimise the need for it but there is often a need for some adjustment whether to ensure that the component reaches the right position or to tighten up a floor after laying.

If you have any questions on barring we would recommend you read the Precast flooring Federations Code of Practice for the Safety Installation of Precast Concrete Floors and Associated Components available here.

The incident to which the title refers occurred in December 2014 when Walter Thompson (Contractors) Limited, a construction company from Northallerton, was engaged as Principal Contractor for a 47 bedroom extension of the Ramside Hall Hotel, Durham.

£33,000 fine under CDM Regulations

An investigation by the Health and Safety Executive (HSE) into the incident found that the company had failed to adequately plan and manage the installation of the two-floor slabs.

The defendants pleaded guilty to breaching Regulation 22(1)(a) of the Construction (Design and Management) Regulations 2007 and was fined £33,000 with £12,552.81 costs.

Contact us on 01453 800100 if you need expert help with health and safety for a fixed cost or use contact us above or the form below to request a proposal;

Contact form

Please complete the form below and we promise to respond within 24 hrs. If you need more urgent help just call 01453 800109 and ask for Andrea.

Posted by Roger Hart
STILL NOT SURE WHAT TO DO?

We are glad that you preferred to contact us. Please fill our short form and one of our friendly team members will contact you back.

X
REQUEST A CALL BACK